WageBid home

SCA vacation and holiday pay: how to price it

Who is owed what under 29 CFR 4.173 and 4.174, why the incumbent crew's seniority becomes your cost, and the math per hour worked.

Every SCA wage determination (WD) lists paid vacation and paid holidays next to the health and welfare (H&W) rate. They look small on the page. In a bid they are not: each week of vacation and each holiday is an hour you pay for but nobody works, and on a staffed post somebody else has to cover it. This guide shows how the rules in 29 CFR 4.173 and 4.174 work and how to turn them into a price.

1. What the WD says

A typical standard WD, such as WD 2015-5233 rev 35 for the Houston area, sets:

The service steps differ between WDs, so read the fringe section of the WD attached to your solicitation. How to read the rest of the WD is in how to read an SCA wage determination.

2. Vacation: service with the predecessor counts

The words "with a contractor or successor" matter most. Under 29 CFR 4.173(a), length of service includes the employee's continuous time with your company (commercial work too) and the time with any predecessor contractors that did similar work at the same federal facility. Prior service as a federal employee does not count.

So if you win a recompete and keep the incumbent janitors, you inherit their seniority. A worker with 6 years on the building is owed 3 weeks of vacation on the anniversary date, even though it is your first day as the contractor.

Four more rules from 4.173 that change the math:

To know what you are taking on, you need hire dates. The incumbent must give the contracting officer a certified list of employees and their anniversary dates at least 10 days before its contract ends, and the contracting officer gives it to the successor when the new contract starts (FAR 52.222-41(n)). That is after you bid, so ask for tenure data in the questions period, and if you get none, assume a mix and say so in your price narrative.

3. Holidays: the workweek rule

Under 29 CFR 4.174(a)(1), an employee who does any work in the week of a named holiday is owed the holiday, even if it falls on a day off. You cannot require a waiting period or work the day before and after unless the WD says so.

4. H&W is owed on vacation and holiday hours too

SCA fringe benefits are owed on all hours paid, up to 40 hours a week and 2,080 a year (29 CFR 4.172). Vacation and holiday hours are hours paid, so H&W keeps running on them (4.173(e)(2)). A full-time employee costs 2,080 hours of H&W per year no matter how much of that is leave.

5. How to put it in the price

There are two common ways, and they give different numbers because they answer different questions.

For bidding, the second method is the one that protects your margin.

Worked example: cost per productive hour for a janitor

Janitor (11150) on WD 2015-5233 rev 35: wage $14.74, H&W $5.92, 11 holidays (88 hours). A full-time worker is paid 2,080 hours a year:

ItemMath$ / year
Wages$14.74 × 2,08030,659.20
H&W$5.92 × 2,08012,313.60
Annual minimum cost42,972.80

Now take off the holiday hours and the vacation hours for the worker's service step, and divide by the hours actually worked:

Service (leave hours)Worked$ / hour
1 to 4 years (88 + 80)1,91222.48
5 to 14 years (88 + 120)1,87222.96
15+ years (88 + 160)1,83223.46

The same janitor is $20.66 per hour paid (wage plus H&W), but $22.48 to $23.46 per hour of coverage. For an incumbent crew of 10 with 4 workers at 2 weeks, 5 at 3 weeks and 1 at 4 weeks, the crew works 18,840 of its 20,800 paid hours, and the blended cost is $429,728 ÷ 18,840 = $22.81 per worked hour. All of this is before payroll taxes, workers' compensation, overhead, G&A and profit, which are covered in how to build a burdened labor rate for an SCA bid.

On a post staffed every day of the year, such as a security post, the holiday hours are not lost: someone works them and is also owed holiday pay. Price those 88 hours per employee as extra cost on top of full coverage.

See the vacation and holidays on your WD

Pick your state and county to see the vacation steps, holidays and H&W on the current WD from SAM.gov.

Open the free WD lookup

Leave hours, priced for you.